LIST OF ON-GOING AND COMPLETED INJECTION SUBSTATION PROJECTS

ITEM NO.
PROJECT DESCRIPTION
LOCATION
         PERCENTAGE        COMPLETION

EXPECTED BENEFITS WHEN COMPLETED
STATUS
1
Ajah-Okeira Kekere, 33KV Overhead Line Ajah /Okeira District
100%
Will stabilize and improve the quality of supply to Customers in Okeira Ado, Badore and Langbasa area. Completed December,
2004
2
Keffi – Fowler 33KV U/G Cable Feeder Keffi/Obalende Islands District
100%

Will stabilize and improve electricity supply to customers in Keffi, Obalende and S.W Ikoyi area.

Completed November, 2004
3
Iganmu – Badia 33KV O/H Line Badia/Amukoko Festac District
100%
Will stabilize and improve the quality of electricity supply to Amukoko/Badia area. Completed February, 2005
4
Mile 2 – Amuwo Odofin 33KV Line Amuwo/Coker Festac District
100%
Will stabilize and improve the quality of electricity supply to Amuwo/Orile Coker area. Completed April, 2005
5
Construction of 4KM Agboju - 4th Avenue Festac Town, Festac District
10%
Will deliver more power to Festac Town area to improve the quality of supply to the customers To be completed by December, 2005
6
Construction of IBA/LASU,
33KV Overhead line

IBA/LASU
AGBARA DISTRICT

10%
Will feed the IBA/LASU 33/11kv Injection Substation to improve the quality of supply in the area.

To be completed by December, 2005

7
Construction of NITEL – Ilupeju 33KV O/H line Mushin Ijora District
20%
Will deliver more power to NITEL Injection substations to improve reliability of supply to Mushin area To be completed by December, 2005
8
Construction f Oniru/Makoro – Anifowoshe 33KV U/G O/H line Victoria Island, Islands District
60%
Will stabilize and improve the quality of electricity supply to Victoria Islands area. To be completed by September, 2005
9
Construction of Amuwo-Kirikiri 33KV O/H line Kirikiri/Tincan, Festac District
10%
Will deliver more power to Kirikiri industrial and Tincan port areas To be completed by October, 2005
10
Construction of Itire – Ijesha Tedo 33KV O/H line Ijeshatedo, Ijora District
10%
Will feed the Ijeshatedo 33/11KV Injection Substation To be completed by December, 2005
11
Reactivation and Rehabilitation of Akangba – NRC express 33KV U/G Feeder Ijora District
80%
Will improve the quality and reliability of supply to Ebute Meta and Yaba area. To be completed by September 2005
12
Reactivation and Rehabilitation of Ijora – Beckley 11 33KV U/G Lagos Island, Islands District
10%
Will stabilize and improve the quality of electricity supply to Lagos Island area To be completed by December 2005

 

ITEM NO.
PROJECT DESCRIPTION
LOCATION
  PERCENTAGE COMPLETION
EXPECTED BENEFITS WHEN COMPLETED
STATUS
1
Okeira - Kekere 1x15MVA, 33/11KV Injection S/S Okeira– Kekere Ajah District
100%
Will stabilize and improve electricity supply to Customers in Oke-ira Ado and Langbasa Badore area. Completed June,
2005
2
Keffi 1x15MVA, 33/11kv Injection S/S Keffi, Ikoyi Islands District
100%
Will stabilize and improve electricity supply to Ikoyi and Obalende area.

Completed December, 2004
3
Badagry 1x15MVA and 1x7.5MVA, 33/11KV Injection S/S Badagry/Agbara District
100%
Will stabilize and improve the quality of electricity supply to Badagry and Ajara area Completed June, 2005
4
Agungi 1x15MVA 33/11kV Injection S/S Agungi/Lekki Ajah District
100%
Will stabilize and improve the quality of electricity supply to Agungi, Maiyegun/Lekki area. Completed July, 2005
5
Ajah Local 1x15MVA Injection Ajah, Ajah District
40%

Will stabilize and improve the quality of Supply to Ajah Town
To be completed by October, 2005
6
4th Avenue 1x15MVA, 33/11KV injection S/S
Festac Town, Festac District
10%

Will stabilize and improve the quality of electricity supply to Festac Town.

To be completed by December, 2005
7
IBA/LASU 1X15MVA 33/11KV Injection S/S IBA/LASU Agbara District
20%
Will stabilize and improve the quality of electricity supply to IBA/LASU Area. To be completed by December, 2005
8
IJESHA– TEDO 1x15MVA, 33/11kv injection S/S. Ijesha – Tedo Ijora District
5%
Will stabilize and improve the quality of electricity supply to Ijesha area. To be completed by December, 2005
9
Replacement of Obsolete 33KV Margini Gallileo Panels at Apapa Road, Local Injection S/S. Apapa, Festac
District
50%
Will stabilize and improve the quality of electricity supply to Apapa area. To be completed by October, 2005
10
Replacement of Obsolete 33KV Margini Gallileo Panel at Custom Injection S/S
Ajele Lagos, Islands District
5%
Will stabilize and improve the quality of Supply to Central Lagos area. To be completed by December, 2005